Friday, 6 May 2011

May 6






Work continues on the office and the bathrooms, getting close to being plumbed and wired.

And Framing, Framing Framing, now we have a bar!!

As well as an unplanned mini-balcony. We've put some outlets up there; eventual plans call for finding a very small DJ or Glenn has offered to find a very small Fiddler.

May 5




Action shots of our two favorite people!! The odds of this project being a success increase with every hour these guys spend there.

The bar is framed, and Andrew (our Electrical Superstar) is drilling the holes for the piping.

May 4



More Framing, Electricians and Plumbers kicking ass, making plans for finishing details, and still managed to find time to visit Dr Parrot and feed the Giraffes at the Oakland Zoo!

May 3



Core Drilling and Plumbing Fun.

Monday, 2 May 2011

May 2



Poor guys are still grinding terrazo! Lovely Columns, Painting out the final dimensions of the bar in preparation for core drilling the holes for plumbing and electric tomorrow.

April 28


Finishing off the floors, got the rear entry done. And making columns. A lot of planning this week, tying up the Landlord's structural items (like floors), talking to Plumbing/Building/Electrical/Health Inspectors, getting final approvals on the plans so we're ready to rumble next week. It's the end of the first quarter, we're ready to blow through the second quarter, and Matt's back from New York on Monday, so we'll start to plan out the second half of the game.

April 27

Grinding Terrazo, back-breaking work!